← All my jobs
In progressJOB-0012
Brackworth Construction Ltd
Marsden House, 40 Ravenscar Yard
Manchester
M17 1QF
11 – 25 Oct 2026
The work
Marsden House refurbishment — heating, phase 1
Strip out and replace the heating installation to floors one and two. Phase 1 of three, invoiced by phase.
Photographs
No photos yet. Site photographs taken here stay with the job — they are not on anyone's phone.
PNG or JPEG. Large photos are resized before upload. 0 of 50 used.
Certificates
- Legionella risk assessmentIssued 05 Dec 2025 · legionella-marsden-house.pdfExpiringExpires 05 Dec 2026
- ElectricalIssued 15 Jul 2026 · eic-marsden-house-phase-1.pdfValidExpires 14 Jul 2031
File a certificate
Give the kind and both dates first, then choose the file.
Money on this job
- Invoiced
- £5,994.00
- Paid
- £0.00
- CIS deduction
- −£778.00
- Outstanding
- £5,216.00